Transport Minister Anthony Loke said the first phase of trials for the Johor Bahru-Singapore RTS Link would begin in December, without passengers. At the time of the update the depot was about 90% complete, Bukit Chagar Station 73% and the ICQ Complex 76.8%. The RTS Operations chief executive said the systems were around 65% ready.
Timeline at the time
Construction was targeted to finish by 31 December 2026, with full operation in January 2027.
Update: a later report in October 2026 said the transit link has been delayed to mid-February. Read it in our news list and check the official operator for confirmed dates before you plan around the opening.
Source: reported by Bernama. Summary and commentary by JBPropertyLaunch.